4253 Locomotive
A not-for-profit company run entirely by volunteers
Contact us at: gwr4253@gmail.com

 

images/300/Facebook logo.jpg

 

 

What's Happening This Month

 

PROGRESS DURING NOVEMBER

WEEK THREE

On Tuesday the cutting out of the new backhead cladding was started,

images/450/Nov 17 1.jpg

the main boiler steam pipe was descaled and inspected and

images/450/Nov 17 2.jpg

the front of the firebox was also descaled.

images/450/Nov 17 3.jpg

On Friday, the brake brackets from the class 108 DMMU were delivered as we had agreed to scrap off years of accumulated crud and then clean and paint them to help progress the refurb.  A start was also made on machining the new brasses for the side rods.

images/450/Nov 17 4.jpg

On Sunday, the DMMU brackets received more paint and a small area of the boiler was heated and dressed to align it with the new throat plate prior to welding in next week.

images/450/Nov 17 5.jpg

More of the backhead cladding was cut out including a 17" diameter hole for which we made a simple jig of a steel strip bolted to the centre point with a hole at the other end to hold and guide the plasma cutter nozzle.

images/450/Nov 17 6.jpg



WEEK TWO

This week we've had a visit from Somers Forge to look at and check dimensions of the two rods we need - we know that someone out there has rods lying around, if you know who they are, please let us know.  The finished tool boxes have been bubble wrapped and placed into storage together with the new bits of cylinder cladding that aren't needed yet.  The firehole door mechanism was taken out of storage and stripped down after some effort so that cleaning up, assessment and overhaul can be undertaken.  We also laid out the rusted pieces of backhead cladding we have to give us a pattern

images/450/Nov 10 1.jpg

after which a start was made on marking out and cutting the new pieces.

images/450/Nov 10 2.jpg

The needle gunning of the inside of the boiler barrel has finally been finished to everyone's relief given the amount of noise and effort involved.

images/450/Nov 10 3.jpg

There has been much other work on the boiler with the foundation ring bolted to the old backhead,

images/450/Nov 10 4.jpg

the lap seams all caukled in (more noise) following the rivet replacement

images/450/Nov 10 5.jpg

and the front of the foundation ring given a final fettling before the throat plate was lifted into position and bolted down to the boiler and the foundation ring.

images/450/Nov 10 6.jpg

It is now ready for the specialist welder to join the sides before we rivet it to the barrel and then fit the palm stays.

images/450/Nov 10 7.jpg

Once that's done it can safely be moved for further work to be undertaken.


WEEK ONE

A lot of effort has been expended this week on needle gunning the inside of the boiler barrel to remove all the old scale which is uncomfortable, unpleasant, tiring and very noisy work so involved a number of people taking turns to spread out the misery.

images/450/Nov 3 1.jpg

Alongside this job various pieces of tooling were being made and trial fitted to hold up the remaining firebox lap seam rivets on the top corners.  Also, the new tool boxes were receiving a final fettling to remove welding blemishes etc. ready for top coating.  The main steam pipe was laid out to measure up for new bolts

images/450/Nov 3 2.jpg

and the longitudinal stays were given a coat of paint.  On Sunday the tool boxes received their first top coat and are looking quite smart.

images/450/Nov 3 3.jpg

The riveting team spent all day putting in the last of the firebox lap seam rivets which numbered less than ten but were extremely difficult to hold up with each of the corner ones needing different blocks, wedges etc. to be constructed so we could get the hydraulic jack to both fit in the gap and sit square on the rivet head.

images/450/Nov 3 4.jpg

The final rivet was supposed to be the easy one - replacing one on the side where access was easy but the pneumatic holding up gun refused to work properly (as did the spare) so it took almost an hour to strip it down, clean all the components, reassemble it and make it work.  The actual rivet replacement took barely 30 seconds.

images/450/Nov 3 5.jpg

Next week isn't likely to be much quieter as we now need to caulk in all those firebox seams.


PROGRESS DURING OCTOBER


WEEK FOUR

This week's work started with the concrete pour for our new entrance ramp

images/450/Oct 27 0.jpg

followed by some floor painting.  The boiler expansion brackets were needle gunned to get the rust out of the hollows on the back that accommodate the boiler's stay heads after which they were given a coat of heat resistant paint.

images/450/Oct 27 1.jpg

In preparation for Sunday's riveting the mobile forge was set up and all necessary air hoses, guns etc. were laid out and tested.  On the day we were therefore able to get an early start on the remaining lap seam rivets on the top front of the firebox.  This is not an easy area to get holding-up tools into as it is restricted as to access and, as the curvature of the firebox doesn't equal that of the boiler, the distances and angles are seldom the same from one rivet to the next.  This had required a number of small blocks of different thicknesses to be cut, drilled and tapped so they could be bolted singly or in combination to a small Enerpac jack to hold up the rivets on the sides while those along the top were done using a pneumatic holding-up tool on various sized blocks.  This also necessitated a trial run with a cold rivet every time to gauge the thickness of block(s) required.  However, apart from that, the job went reasonably quickly with the rivets heated,

images/450/Oct 27 2.jpg

passed down into the boiler,

images/450/Oct 27 3.jpg

where they were inserted into the hole

images/450/Oct 27 4.jpg

and the holding-up tool pumped to force them into position

images/450/Oct 27 5.jpg

whereupon they were then hammered down with the rivet gun from inside the firebox.

images/450/Oct 27 6.jpg

By day's end we just had the corner ones to do and, given these are the most difficult to hold up, special tooling will have to be made up next week before we can complete the job.  Once finished we can then fit the throatplate and palm stays.


WEEK THREE

This week started with digging out some of the floor in the entrance to the construction booth so we can change it from steps to a ramp which will make life easier for getting heavy items in and out.

images/450/Oct 20 1.jpg

The shuttering is all in place and the concrete gets poured next week.  Also, as part of last week's clear up of the boiler house, we ended up with a bucket full of odd nuts and bolts that had been lying around and these have all been sorted into sizes and put back in stock.  The cab tool boxes are nearing completion with the lid holding arrangement for the larger box finished and undercoated

images/450/Oct 20 2.jpg

and the catch for the smaller one having been made and welded on.

images/450/Oct 20 3.jpg

This shot shows the larger getting its final undercoat while the smaller is being worked on in the background.  It also shows our new tool storage racks which are already proving their worth in time saved finding the right spanner etc.

images/450/Oct 20 4.jpg

The boiler expansion brackets were taken out of storage to be cleaned up and inspected and it took almost as long to find them as it did to do the job.  They were of course in the furthest, darkest corner buried under everything else.  

images/450/Oct 20 5.jpg

The refurbishment of the sheet guillotine machine has been completed including painting and it just needs reassembly now.



WEEK TWO

We have acquired an old plate guillotine which, this week, was stripped down, assessed and all the old paint stripped off.

images/450/Oct 13 1.jpg

It appears to be in quite good nick and, after re-tapping some threads and freeing off other parts, the components were given a coat of red oxide.  The axle for the 08 diesel received its final coat of gloss and now awaits refitting.  Tool box work continues with the front lips of the lids receiving some more weld on the join and then being ground back to give a smooth finish.

images/450/Oct 13 2.jpg

A rod and catch mechanism to hold the lid open has been made for one box and welded in place and the second one started.  The first of the new crank pin nuts has had the groove for the Belleville washer machined into it

images/450/Oct 13 3.jpg

and, later in the week, the guillotine parts received a coat of gloss

images/450/Oct 13 4.jpg

as did the inside of the tool boxes.

images/450/Oct 13 5.jpg

We have also had a good clear out of the boiler house which has been slowly filling up, with many items mysteriously appearing unannounced!  This has provided sufficient room for the portable forge to be moved in in preparation for replacing the remaining firebox lap seam rivets.



WEEK ONE

One of our side jobs this week was painting the axle that's currently out of the 350 diesel shunter but, given how wet the weather's turned, we first erected one of our gazebos over it.

images/450/Oct 6 1.jpg

Back at 4253, the fire grate carriers were cleaned up and assessed,

images/450/Oct 6 2.jpg

the last of the vacuum retaining valve pipework union and hose tails was machined up and the side rod crank pin nuts have been measured prior to the next machining operation.  Most of this week's work has been directed at the cab tool boxes with closing lips cut and welded to the bottom edge of the lids, the hinges being radiused and countersunk before being bolted on,

images/450/Oct 6 3.jpg

hasps being made

images/450/Oct 6 4.jpg

and the boxes drilled to accept both hasps and the padlock rings.

images/450/Oct 6 5.jpg

Additionally, the tank and bunker water space access plates have had rubber gaskets cut to fit.

images/450/Oct 6 6.jpg