Progress March 2026

Week Two Work on the front cab window hinges of 4253 continued with the hinges drilled, countersunk and fitted to the frames  after which they were clamped to a section of angle to check that the window could swing freely. The stud holes in the foundation ring for attaching the ashpan were cleaned out and measured so a set of … Read More

Progress February 2026

Week Four On Tuesday, 5164’s bunker work included welding a thin strip to the top of the centre baffle as it was sitting slightly lower then the two side baffles.   The coal hole door slides were also bolted into place in preparation for riveting  and all the rivets put in last week received a clean up to remove any traces … Read More

Progress January 2026

Week Four This week, yet more clever shaped cladding bits were cut out and bent and more cones for the washout plug areas were made. The driver’s side corner pieces have now all been made to below floor level so the end of this job is now in sight.  We also trial fitted a few bits we’d made some years back … Read More

Progress December 2025

Final Week This week, Tuesday involved manning the sales stand at the Santa Specials, Friday was Boxing Day, so only Sunday was an on-the-tools day and, although we only had four people for that, it was a productive day.  We started off by constructing a building bench for 5164’s bunker so we could work on setting out the floor panel, lifted … Read More

Progress November 2025

Final Week With the Santa Specials trains starting this weekend, the trailer was loaded up with all the Sales Stand gear and moved up to Tenterden where our new gazebo was erected, the raised floor installed and all the tables, wiring etc. set up ready for the weekend. Typically, it rained for most of Saturday which always adversely affects how … Read More

Progress October 2025

Week Four The long job of fabricating all the joining pieces between the shoulders of the firebox and backhead cladding continued this week with more bits being measured, cut, bent, screwed and welded together. The new oil lubrication pipe cover that fits on the smokebox side was trial fitted to mark the holes that need cutting out to allow the … Read More

Progress September 2025

Week Four This week started with taking apart the old ducket from 5164’s bunker which involved a lot of drilling, cutting, rivet removal and hammering before it surrendered.  We then offered it up to the new platework and it’s a decent fit that will just require a little trimming and fettling before we can integrate it. Next job was fitting the … Read More

Progress August 2025

Final Week An extra day was worked on Monday this week with 4253’s cab and fireman’s side tank removed  so a few rivet heads could be dressed back to prevent contact  after which the tank and cab went back on.  On Tuesday, the steam manifold was lifted into place so the position of the opening required in the cab front plate … Read More